QUEST A comparison of completion status to baseline is referred to as _____.
A Earned value measurement.
B Percent complete.
C ACWP.
D BCWS
E None of above.
A
QUEST The logical relationship that communicates a delay between the start/finish of one activity and the start/finish of another activity is referred to as:
A Slack
B Free float.
C Restricted float.
D Level float.
E Lag
E
QUEST Overlapping activities on a project, such as design and construction, is referred to as:
A Fast tracking
B Risk conversion.
C Parallel management.
D Process improvement.
E Synchronous manufacturing
A
QUEST A computer tape which contains historical project information is called ____ tape.
A Database
B Baseline.
C Archive.
D Lessons learned.
E Life cycle summary.
C
QUEST Which method shown below is acceptable for reducing cost or shortening the schedule?
A "Crashing"
B Changing scope.
C Performing activities in parallel rather than in series.
D All of the above.
E A and C only.
D
QUEST In general, attempts to smooth out period to period resources will _____ the scheduled time and _____ project costs.
A Increase, decrease.
B Increase, increase
C Increase, increase or decrease.
D Decrease, decrease.
E Decrease, increase.
B