QUEST In the arrow diagramming method (ADM), _____ do not consume time or resources.
A Events.
B Activities
C Slack elements.
D B and C only.
E All of the above.
A
QUEST On a precedence diagram, the arrow between two boxes is called:
A An activity.
B A constraint.
C An event.
D The critical path.
E None of above.
B
QUEST A project element which lies between two events is called:
A An activity.
B A critical path method.
C A slack milestone.
D A timing slot.
E A calendar completion point.
A
QUEST The basic terminology for networks includes:
A Activities, events, manpower, skill levels and slack.
B Activities, documentation, events, manpower and skill levels.
C Slack, activities, events, and time estimates.
D Time estimates, slack, sponsorship involvement, and activities.
E Time estimates, slack time, report writing, life cycle phases, and crashing times.
C
QUEST The utility of network-based schedules:
A Reveals interdependencies.
B Facilitates "what if" exercises.
C Highlights critical activities.
D Provides information on resource requirements, time requirements and tradeoffs.
E All of the above.
E
QUEST The major disadvantage of a bar chart is:
A Lack of time-phasing.
B Cannot be related to calendar dates.
C does not show activity interrelationships.
D Cannot be related to manpower planning.
E Cannot be related to cost estimates.
C