首页 诗词 字典 板报 句子 名言 友答 励志 学校 网站地图
当前位置: 首页 > 职业资格 > 项目管理 > PMP >

2012年pmp考试模拟题05(附答案)(1)

2012-05-16 
pmp考试模拟试题及答案(五)

  QUEST A line manager provides you with three estimates for his activity in your PERT network. His estimates are 2 weeks optimistically, 4 weeks most likely, and 12 weeks pessimistically. The expected time which would appear on the chart would be:

  A 4 weeks

  B 5 weeks

  C 6 weeks

  D 7 weeks

  E None of the above.

  B

  QUEST Management has decided to "crash" a project in order to avoid penalty payments for late deliveries. To crash the project, either overtime or additional resources should be assigned to:

  A All activities.

  B Only those activities with the longest time durations.

  C Those activities on the critical path begining with the longest time duration activities.

  D Those activities with the greatest degree of risk.

  E None of the above.

  C

  QUEST A network has been developed with resources from six different departments. One of the six departments has just informed you that they can increase the number of employees from 5 to 8. This will result in:

  A A shortening of the critical path.

  B A shortening of the noncritical path.

  C A decrease in the total cost of the project.

  D An increase in the cost of the project.

  E A through D are possible based upon where the resources are deployed.

  E

  QUEST Bar charts are most appropriate for:

  A Comparing actual to planned performance to each activity.

  B Showing slack time.

  C Showing critical path dependencies.

  D Showing which activities can be rearranged in parallel.

  E All of the above.

  A

  QUEST A non-critical path activity is completed in half the time. Then,

  A The critical path is also reduced.

  B The slack in the path containing this activity will increase.

  C The total cost for this activity has decreased.

  D Manpower from this activity can be assigned to other activities.

  E All of the above.

  B

  QUEST Once the logic of a network is laid out, the project manager will conduct a forward pass and backward pass through the network. This will provide information on the _____ and identification of the _____ .

  A Slack for each activity, critical path.

  B Slack for each activity, high risk activities.

  C Manpower shortages, high risk activities.

  D High risk activities, non-critical paths.

  E Manpower availability, contingency plans.

  A

热点排行