首页 诗词 字典 板报 句子 名言 友答 励志 学校 网站地图
当前位置: 首页 > 职业资格 > 项目管理 > PMP >

2012年pmp考试模拟题04(附答案)(1)

2012-05-16 
pmp考试模拟试题及答案(四)

  QUEST Resource leveling _____.

  A Allocates resources to activities to find shortest schedule within fixed resource limits.

  B Smoothes out resource requirements by rescheduling activities within their float time.

  C Smooths out resource requirements by substituting activities with unassigned resources.

  D Attempts to reduce resource requirements within a constraint on project duration

  E B or D

  E

  QUEST A(n) _____ is defined as a specified accomplishment in a particular instant in time which does not consume time or resources.

  A Activity

  B Event.

  C Correlation

  D Constant

  E Event constrained within planned effort.

  B

  QUEST Which of the following impacts the critical path?

  A Changing the task duration.

  B Reduce the free float of an activity.

  C Executing a backward pass

  D A or B

  E None of the above.

  A

  QUEST The range of time allowed for an activity to be completed in is the _____.

  A Planned time (Duration).

  B Float time (LS - ES, or LF - EF).

  C Critical time (when ES = LS, or EF = LF).

  D Scheduled time (LF - ES).

  E Event.

  D

  QUEST Free float is the amount of time that an activity may be delayed with out affecting the _____.

  A Early start of the succeeding activities.

  B Late start of the succeeding activities.

  C Project finish.

  D Cost of the project.

  E None of the above.

  A

  QUEST Using the problem stated in the Special window, Calculate the deviation of duration for the task, using the PERT concept of standard deviation of task duration.

  A 0.5

  B 1

  C 1.8

  D 2.2

  E 2.8

  C

  QUEST In crashing a task, you would focus on:

  A As many tasks as possible.

  B Non critical tasks.

  C Accelerating performance of tasks on critical path.

  D Accelerate performance by minimizing cost.

  E A and D.

  C

  QUEST Using the problem stated in the Special window, Calculate the expected value of duration (in days) using the PERT concept of the expected duration of a task

  A 8

  B 8.8

  C 9.1

  D 9.7

  E 10.5

  B

  QUEST Using the WBS in the Special window, an instance of a work package is:

  A Build house

  B Excavate

  C Prepare Foundation

  D B and C

  E None of the above

  E

热点排行