2012年pmp考试模拟题04(附答案)(5)

2012-05-16 
pmp考试模拟试题及答案(四)

  QUEST Your team has prepared a CPM schedule for your review. You notice that one node has six inputs (including two dummy activities) and four outputs (which include one dummy activity). Select the correct statement from the following:

  A This is a valid representation if the logic is correct.

  B This is invalid because a node can have a maximum of one dummy input representation if the logic is correct.

  C This is invalid because nodes cannot have both dummy inputs and dummy outputs.

  D This is a invalid because the number of outputs must equal the number of inputs.

  E This is invalid because a maximum of two inputs and two outputs are allowed using the critical path method.

  A

  QUEST During project execution, the customer authorizes and funds a scope change which requires a major change in the schedule. The baseline schedule:

  A Now becomes the new schedule, including the changes, and the original baseline is disregarded.

  B Is still the original baseline but annotated to reflect that a change has taken place.

  C Is amended to reflect the scope change, but the original baseline is still maintained for post-project review.

  D Is meaningless since every schedule update changes the baseline (i.e., a rubber baseline.)

  E Is the same since baseline schedules cannot change once the development phase is completed.

  C

  QUEST Network schedules are prepared during the _____ phase and updated during the _____ phase.

  A Conceptual, execution.

  B Development, implementation.

  C Development, close-out.

  D Implementation, close-out.

  E Planning, finishing.

  B

  QUEST Scheduling systems such as PERT, ADM, and PDM are project management tools to be used by:

  A The project manager and project office personnel.

  B The project team and functional managers.

  C The project sponsor.

  D All of the above.

  E A and B only.

  E

  QUEST Increasing resources on the critical path activities may not always shorten the length of the project because:

  A Certain activities are time-dependent rather than resource-dependent (i.e., using three ovens rather than one to bake a cake).

  B Safety, OSHA and EPA may have placed restrictions on the number of people used on certain activities or in the physical location of the project.

  C The skill level of the added resources might not be appropriate for the activities to be performed.

  D Adding more resources may create additional work and produce inefficiencies (i.e., additional people may need training and supervision.)

  E All of the above.

  E