2012年pmp考试模拟题04(附答案)(4)

2012-05-16 
pmp考试模拟试题及答案(四)

  QUEST Using the figure in the Special window, The Critical path is _____ weeks.

  A 21

  B 22

  C 23

  D 24

  E 25

  D

  QUEST Using the data shown in the Special window, Activities P, Q, and T are critical path activities. In order to shorten the time duration of the project, which activity should be "crashed" first?

  A P

  B Q

  C R

  D S

  E T

  A

  QUEST Using the figure in the Special window, By how many weeks can activity "F" slip without extending the end date of the project?

  A 0

  B 1

  C 2

  D 3

  E 4

  D

  QUEST Using the figure in the Special window, The critical path is:

  A A-B-G

  B C-G

  C C-D

  D E-F

  E A-B-G and C-D

  B

  QUEST The first step in building a PERT/CPM network is to:

  A Create a flow chart

  B Determine the critical path

  C Show task relationships

  D Create a work breakdown structure

  E None of the above.

  D

  QUEST The critical path in a schedule network is the path that:

  A Takes the longest time to complete

  B Must be done before any other tasks

  C Allows some flexibility in scheduling a start time.

  D Is not affected by schedule slippage

  E All of the above.

  A

  QUEST Assume that you have a network where an activity on the critical path can be crashed by two weeks. If the activity is actually crashed by two weeks, then:

  A The project's schedule will be reduced by 2 weeks.

  B The available slack on the noncritical paths will increase.

  C A new critical path may appear after the crash.

  D All of the above.

  E A and B only.

  C