  QUEST The purpose of a dummy activity in an activity-on-arrow diagram is to:

  A Identify a task that could be replaced by another.

  B Take the slack time into account.

  C Show a task that is not necessarily needed.

  D Denote a milestone.

  E Show a dependency relationship.

  E

  QUEST On November 1, $1000 worth of work on task A was supposed to have been done (BCWS); however, the BCWP was $850. Calculate the schedule variance:

  A ¥-100

  B ¥100

  C ¥-150

  D ¥150

  E 85%

  C

  QUEST A plan has budgeted three weeks of effort for consultants, but the job was done in only two weeks. Calculate the variance:

  A 1.50%

  B 33.00%

  C 75%

  D 67%

  E None of the above.

  B

  QUEST Resource leveling will often affect the project by making it:

  A Shorter.

  B Longer

  C More responsive to customer needs.

  D A and C

  E B and C.

  B

  QUEST Using the figure in the Special window, The slacktime in Activity "G" is _____ weeks.

  A 2

  B 3

  C 4

  D 5

  E 7

  C

  QUEST Using the figure in the Special window, Activity "D" has a latest start time of _____ weeks and a latest finish time of _____ weeks.

  A 2, 10

  B 4, 12

  C 6, 14

  D 7, 15

  E 9, 17

  A

  QUEST Using the figure in the Special window, Activity "L" has an early start time of _____ weeks and an early finish time of _____ weeks.

  A 11, 13

  B 12, 14

  C 13, 15

  D 14, 16

  E 15, 17

  E