2012年pmp考试模拟题05(附答案)(2)

2012-05-16 
pmp考试模拟试题及答案(五)

  QUEST ADM is an activity-on-arrow method. In this method, a dummy activity:

  A Denotes a critical path relationship.

  B Denotes any dependency relationship.

  C Shows slack.

  D Identifies customer deliverables dates.

  E Identifies customer team meeting dates.

  B

  QUEST The starting point in the development of a top-down PERT/CPM chart is the _____ .

  A Project specification tree.

  B Customer's deliverable list.

  C Customer's milestone dates.

  D Work breakdown structure.

  E Listing of customer team meeting dates.

  D

  QUEST The critical path in a network is the path that:

  A Has the greatest degree of risk.

  B Will elongate the project if the activities on this path take longer than anticipated.

  C Must be completed before all other paths.

  D All of the above.

  E A and B only.

  B

  QUEST The major difference between PERT and CPM networks is:

  A PERT requires three time estimates whereas CPM requires one time estimate.

  B PERT is used for construction projects whereas CPM is used for R & D.

  C PERT addresses only time whereas CPM also includes cost and resource availability.

  D PERT requires computer solutions whereas CPM is a manual technique.

  E PERT is measured in days whereas CPM uses weeks or months.

  A

  QUEST A calendar that identifies when a project may be performed on an activity is called a:

  A Project calendar.

  B Resource calendar.

  C Milestone point.

  D Key point.

  E Work unit.

  A

  QUEST Planning activities such that predetermined resource availability pools are not exceeded is called:

  A Resource leveling.

  B Manpower leveling.

  C Resource limited planning.

  D Manpower planning.

  E Manpower contingency planning.

  C