  QUEST The most common types of schedules are Gantt charts, milestone charts, line of balance, and:

  A Networks.

  B Time phased events.

  C Calendar integrated activities.

  D A and C only.

  E B and C only.

  A

  QUEST Scheduling is the process by which decisions are made concerning:

  A Tasks to be accomplished.

  B Personnel/organization that will be assigned to accomplish the task.

  C Time when the tasks are to be completed.

  D All of the above.

  E A and C only.

  E

  QUEST Time management is the allocation of time in a project's life cycle through the process of:

  A Planning

  B Estimating.

  C Scheduling.

  D Controlling

  E All of the above.

  E

  QUEST Using the situation shown in the Special window and assuming continues efficiency for work-in-progress and fixed price contract for task four. The estimate at completion is:

  A $19K

  B $21K

  C $26K

  D $29K

  E indeterminate

  C

  QUEST Using the situation stated in the Special window, a comparison of the cost variance of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____.

  A Become worse, become worse

  B Become worse, improved

  C Improved, increased

  D Improved, become worse

  E None of the above are correct

  B

  QUEST The computation for Cost Performance Index is:

  A BCWP/ACWP

  B BCWP-ACWP

  C BCWP-BCWS

  D ACWP/BCWP

  E ACWP-BCWS

  A