  QUEST Work packages are used to:

  A Represent units of work at a level where work is performed.

  B Clearly distinguish one work package from all others assigned to a single functional group.

  C Limit the work to be performed to relatively short periods of time.

  D All of the above.

  E A and B only

  D

  QUEST Project life cycles are very useful for _____ and _____ .

  A Configuration management, termination

  B Objective setting, information gathering

  C Standardization, control

  D Configuration management, weekly status updates

  E Approval, termination

  C

  QUEST Which of the following are included as part of a scope statement?

  A Project justification

  B Project deliverables

  C Project objectives

  D All of the above

  E B and C

  D

  QUEST The initial document that formally recognizes the existence of a project is the _____ .

  A Scope baseline

  B Management plan

  C Project charter

  D Configuration control report

  E None of the above

  C

  QUEST Which of the following is not a scope management process?

  A Initiation

  B Scope planning

  C Scope Definition

  D Scope change control

  E Scope verification

  D

  QUEST In which of the following scope management processes is the scope management plan prepared?

  A Initiation

  B Scope planning

  C Scope Definition

  D Scope change control

  E Scope verification

  B

  QUEST The project charter is prepared in which scope management process?

  A Initiation

  B Scope planning

  C Scope Definition

  D Scope change control

  E Scope verification

  A

  QUEST The work breakdown structure (WBS) is first developed in which scope management process?

  A Initiation

  B Scope planning

  C Scope change control

  D Scope Definition

  E Scope verification

  D

  QUEST In which of the following scope management processes are subject matter experts used?

  A Initiation

  B Scope planning

  C Scope Definition

  D Scope change control

  E Scope verification

  A

  QUEST A Work Berakdown Structure is most useful for:

  A Identifying individual tasks for a project.

  B Scheduling the start of tasks.

  C Developing a cost estimate.

  D Determining potential delays.

  E A and C.

  E

  QUEST The scope statement provides

  A A basis for future decisions about a project.

  B A baseline to accomplish verification measures.

  C A baseline to evaluate potential scope changes.

  D All of the above

  E B and C only

  D

  QUEST A work breakdown structure:

  A assures all work is identified.

  B subdivides the project into manageable segments.

  C provides the project sponsor with a time-phase task summary.

  D both A and B.

  E All of the above.

  D

  QUEST Budgetary estimates are the output of the _____ phase(s) of the project.

  A conceptual

  B development

  C implementation

  D finish

  E All of the above.

  B

  QUEST Which of the following are included in the Acquisition phase(s) of the project life cycle.

  A concept and development

  B development and planning

  C execution and phase-out

  D planning and implementation

  E concept and planning

  C

  QUEST Project alternatives are examined during the _____ phase of the project

  A conceptual

  B finish

  C development

  D implementation

  E A and C

  E

  QUEST We assign human and non-human resources in the _____ phase of the budget.

  A conceptual

  B planning

  C development

  D implementation

  E close-out

  D

  QUEST Project trade-offs vary between

  A risk, cost and schedule.

  B direct cost, indirect cost, and resource availability

  C quality, schedule and time

  D cost, quality and schedule

  E contract terms, scope and budget

  D

  QUEST The extent of project management techniques to be used on a project are determined mainly by the _____ and _____ of the project.

  A budget, schedule

  B quality requirements, schedule

  C size, type of industry

  D nature, size

  E project manager, sponsor

  D