  QUEST The use of the project reports:

  A are not necessary on small projects

  B provides a means whereby various levels of authority can judge project performance

  C provides insight into project areas and the effectiveness of the control systems

  D All of the above

  E B and C

  E

  QUEST Documented work authorization provide:

  A a means of effective internal coordination of the project’s activities.

  B an audit trail of all work authorized from project initiation to completion.

  C a means for communication of work activity between the project manager and the performing

  activities.

  D All of the above

  E A and B only.

  D

  QUEST The project life-cycle can be described as:

  A project concept, project planning, project execution, and project close-out.

  B project planning, work authorization, and project reporting.

  C project planning, project control, project definition, WBS development, and project

  termination.

  D project concept, project execution, and project reporting.

  E All of the above.

  A

  QUEST A Work Breakdown Structure:

  A assures all work is identified

  B subdivides the project into manageable segments

  C provides the project sponsor with a time-phase task summary

  D both A and B

  E All of the above.

  D

  QUEST Scope Management:

  A entails managing the project’s work content.

  B is a subset of configuration management and as such is performed by CM specialists.

  C is concerned with naming all activities performed, the end products which results and the

  resources consumed.

  D is not a concern of the project manager.

  E None of the above.

  C

  QUEST Feasibility studies occur in which life cycle phase (s)?

  A Conceptual

  B Conceptual or Development

  C Execution

  D Preliminary planning

  E any life cycle phase

  A

  QUEST Good project objectives must be:

  A General rather than specific

  B Established without considering resource bounds

  C Realistic and attainable

  D Overly complex

  E Measurable, intangible and verifiable

  C

  QUEST Researching, organizing and recording pertinent information is called:

  A Alternative analysis

  B Information gathering

  C Configuration management

  D Post project analysis

  E All of the above

  B

  QUEST The Work Breakdown Structure (WBS) is the basis for communicating:

  A Project scope, cost control, schedule, quality

  B Project objectives, dependencies, plan, cost control

  C Project scope, schedule, staffing, cost control

  D Project scope, quality, schedule, dependencies

  E Project budget, schedule, risk factors, work assignments.

  A