首页 诗词 字典 板报 句子 名言 友答 励志 学校 网站地图
当前位置: 首页 > 职业资格 > 项目管理 > PMP >

2012年pmp考试模拟题03(附答案)(3)

2012-05-12 
pmp考试模拟试题及答案(三)

  QUEST A completion of a local government study resides on your critical path. This would most

  likely be referred to as:

  A Soft logic

  B Hard logic

  C An external dependency

  D A mandatory dependency

  E A lost cause

  C

  QUEST Which of the following can affect network durations?

  A Skills of the resource pool

  B Calendar dates

  C Constraints

  D All of the above

  E A and B only

  E

  QUEST Sources for data on activity durations and resource requirements can be gathered from

  which of the following:

  A Past project records (historical data)

  B Commercial techniques (standard practices, rules of thumb)

  C Past project team members knowledge (experience, oldtimers)

  D All of the above

  E A and C only

  D

  QUEST The erection of foundation formwork before the placement of foundation concrete would be

  an example of a _____ dependency.

  A Discretionary

  B Mandatory

  C External

  D Soft logic

  E Subcontracted

  B

  QUEST "Hard logic" in the preparation of a network refers to:

  A Discretionay dependencies

  B External depenencies

  C Mandatory dependencies

  D All of the above

  E A abd B only

  C

  QUEST The difference between a project and a program is that:

  A A program is made up of multiple projects

  B A program requires at least three times longer to plan than a project

  C A project is a one-shot deal while a program is on-going

  D A and C

  E B and C

  D

  QUEST As a control tool, the bar chart (Gantt) methods is most beneficial for:

  A rearranging conflicting tasks

  B depicting actual versus planned tasks

  C showing the outer dependencies of tasks

  D A and C.

  E A and D

  B

  QUEST You are managing an internal project where a vice president from the user group is acting

  as the sponsor. You have just been informed by your team that the critical path has slipped by

  three weeks. You should:

  A Immediately inform the sponsor and ask for advice

  B Do nothing until the slippage occurs

  C See the sponsor after you have evaluated alternatives, recommendations, and performed an

  impact analysis

  D Look for someone to blame before you see the sponsor

  E Inform your senior management of the problem and tell them that you will get back to them

  after you assessed the situation

  C

  QUEST Line of balance charts are used most frequently in:

  A Engineering

  B Marketing

  C Manufacturing

  D Accounting

  E Contracts and procurement

  C

  QUEST Which of the following is indicative of negative float?

  A The late start date is earlier than the early start date.

  B The critical path supports the imposed end date.

  C The early finish date is equal to the late finish date.

  D When leads are employed in the schedule.

  E The project is sinking.

  A

  QUEST The most frequently used construct in Precedent Diagramming Method is:

  A Start to Start.

  B Finish to Finish.

  C Start to Finish.

  D Finish to Start.

  E Dummy activity.

  D

  QUEST The critical path is calculated by

  A subtracting the end date of task one from the start date of task two.

  B determining which tasks have the least amount of total slack.

  C totaling the time for all activities.

  D determining the shortest path through the network.

  E Determining which tasks have the most slack

  B

  QUEST Using the table in the Special window, Which task is completed?

  A dig hole

  B remove debris

  C survey

  D set forms

  E place concrete

  B

  QUEST Which may be employed to shorten a schedule without changing the scope of the task?

  A Fast tracking.

  B Crashing

  C Releasing resources earlier from tasks which were scheduled with a late start.

  D Alter to task priorities.

  E A or B

  A

热点排行