首页 诗词 字典 板报 句子 名言 友答 励志 学校 网站地图
当前位置: 首页 > 财会考试 > ACCA/CAT > 历年真题 >

ACCA2012年6月份考试真题及答案解析(P3)(11)

2013-04-25 
读书人网精心为大家整理了ACCA2012年6月份考试真题及答案解析(P3),希望对大家的考试能带来帮助!

It was also recognised that requirements are likely to change in the long term. There is no guarantee that the software vendor

  will develop the package to fit newly emerging requirements and so the issues of tailoring and work-around will again have

  to be considered. Most package selection takes place against current requirements and so this approach is well-suited to

  circumstances where requirements rarely change and, if they do, they are specified by legislative bodies and the software

  vendors must make the changes to keep their product compliant. Payroll and integrated accounts applications are typical of

  this. Applications that are subject to long-term changes (such as the production process at Flexipipe) and do not require

  legislative compliance, are less appropriate to this approach.

  Absence of mature procurement process and management expertise

  It was recognised from the outset that Flexipipe did not have an established process for software package selection and

  implementation. This was a very risky project in which to try and establish a process and select an appropriate package. Lack

  of procurement expertise in general has been a problem in the past for the company when a key supplier of raw materials

  for the pipes went out of business. This caused short-term production problems, although an alternative supplier had

  eventually been found. However, procurement still only employs two people full-time and they are relatively junior and overworked. The company appears to have a very immature procurement process.

  The long-term commitment to an external supplier is very problematic in software supply, where moving formerly in-house

  applications to a new supplier can be technically difficult, expensive and disruptive. In general, there are significant risks

  associated with the long-term viability of software suppliers and the maintenance of software applications that are critical to

  the company. Companies go out of business, as in the case study scenario, and companies are sold. It is feasible that a

  software supplier might be bought by a competitor of Flexipipe, threatening long-term supply. These problems are largely

  absent in bespoke development, particularly if this development is undertaken in-house. The software program code belongs

  to the company (not the supplier) and its long-term development is under its control.

  (b) In the context of the Flexipipe project, here are some of the issues that could have been addressed by a formal software

  package evaluation process. It is important that candidates identify elements of the process relevant to the Flexipipe scenario.

  A generic evaluation process is insufficient.

  18The business case for all software procurement projects should be assessed to see if a package is an appropriate solution.

  In some instances a bespoke IT development may be better suited. As mentioned in the answer to the first part of this

  question, the Harmon grid considers process complexity and strategic importance and it could have been used as a guide to

  assessing the appropriateness of the software package solution approach. If it had been used at Flexipipe then it seems likely

  that the software package approach would have been abandoned at an early stage of the project.

  The requirements must be carefully and comprehensively specified before embarking on a procurement exercise. Difficulties

  with specifying requirements may again lead to a re-consideration of the bespoke approach. In the case study scenario,

  mention is made of the system failing to fulfil a number of functional requirements, such as monitoring process variance. The

  inference is that these requirements were either not specified or were incorrectly specified in advance and so were not part

  of the package assessment. Similarly, problems with ‘usability’ may be due to the failure of defining specific usability

  requirements in advance and so these were not considered when the package was evaluated.

  The tendering method has to be made more formal and competitive. A post-project review has shown that there were at least

  three other packages which should have been considered in the evaluation process. A more formal process would have had

  a mechanism for finding these potential suppliers. The openness of the tendering process would also have been assisted by

  advertising in trade magazines and internet tendering sites, which may have also brought forward other potential suppliers.

  This is an important step because it allows a transparency in the process, and avoids selecting a supplier purely on the

  recommendation of one internal employee: as in the case of Flexipipe. It would have avoided the situation of a package being

  selected solely on the basis of a visit to an exhibition.

  Suppliers who submit tenders must be evaluated against criteria agreed in advance. Buying a software package leads to a

  long-term relationship between the supplier and the customer, so the latter must be comfortable with the supplier’s

  credentials. In the context of Flexipipe this would involve setting standard measures and minimum values for liquidity, gearing

  and profitability. There also has to be some way of off-setting the supplier’s suitability with the suitability of the product. That

  is, how a package with limited functionality from a well-established, financially sound supplier is evaluated against a more

  functional, usable package from a newly established company with high financial gearing and low turnover. The balance

  between such factors has to be established in advance, often using a high-level weighted matrix. In the context of the

  scenario, appropriate financial checks should have identified the high gearing and poor liquidity of the supplier that eventually

  led to its collapse.

  A proper process also needs to be in place to evaluate the potential solution against the specified requirements. It is

  important to establish the ‘fit’ between the requirements and the potential solution and to use this ‘fit’ in the final selection.

  It has been stated elsewhere that it is unlikely that a package solution will exactly fulfil all requirements. However, if the ‘fit’

  is known and understood in advance then negotiation with users may lead to them dropping, modifying or finding workaround for these gaps. Perhaps some of the functional shortcomings identified by users might have been tolerated, if they had

  been known and understood in advance.

  Finally, a planned implementation is an important part of the process. Perhaps the lack of usability of the software was down

  to the absence of training and the belief that users could ‘to pick up the software as they go along’. This is a risky approach,

  even in circumstances even with experienced users and in a situation where the software product is a good fit with their

  requirements.

  

热点排行