PMP认证考试试题及答案(五十四)

2010-09-08 
读书人职业资格频道职业资格考试专业网站 http://www.reader8.com/exam/zige/ 在10月24日要举行PMP第四次考试,离考试的时间越来越近,不知道考生有没有准备好,在这里编辑整理了一些PMP的练习题,希望能对考生有所帮助。也

读书人职业资格频道 职业资格考试专业网站 http://www.reader8.com/exam/zige/

在10月24日要举行PMP第四次考试,离考试的时间越来越近,不知道考生有没有准备好,在这里编辑整理了一些PMP的练习题,希望能对考生有所帮助。也希望考生能顺利通过考试。 1 Which of the following control types has the highest risk to the owner:
A Firm fixed price (FFP)
B Time and material (T&M)
C Cost plus fixed fee (CPFF)
D Cost plus incentive fee (CPIF)
E A and B only
B
2 Which of the following contract types has the highest risk to the contractor:
A Firm fixed price (FFP)
B Time and material (T&M)
C Cost plus fixed fee (CPFF) 来源:考试大
D Cost plus incentive fee (CPIF)
E A and B only
A
3 Arbitration is a _____ approach to conflict management in resolving conflict disputes.
A lose-lose
B win-win
C win-lose
D lose-win
E closed door
A
4 Which of the following is not a method of government procurement.
A Assistance
B sealed bidding
C competitive proposals
D acquisition
E small purchases
D
5 The review for the specification completeness is performed during which of the following cycles.
A Award cycles
B requirements cycle
C requisition cycle
D solicitation cycle
E contractual cycle
C
6 In which of the following is the cost of risk hidden by the contractor?
A Firm Fixed Price Contract
B Fixed Price Plus Incentive
C Cost Plus Fixed Price
D Cost Plus Percentage of Cost
E A and B
D
7 The definitive terms of a contract are written during which of the following contract phases?
A Contract Phase
B Post-Award Phase
C Award Phase
D Pre-Award Phase
E Requirement Phase
C
8 The _____ specification delineates specific end use capabilities which can be tested in the acceptance procedure.
A performance
B functional
C technical
D base line http://ks.examda.com
E operational
B
9 Which one of the following is not an acquisition method?
A advertising
B invitation
C negotiation
D purchase
E all are acquisition methods
A
10 Which is not a negotiation tactic?
A Imposing deadlines
B surprises
C person with authority is absent
D reasoning together
E all are negotiations tactics
E
11 A warranty may not be a remedy for products delivered unfit when _____ .
A the PM has knowledge of the product, inspected it without relying on the seller's skill
B the products delivered comply with the plans and specifications of the client
C the plans and specifications produced by the seller match the completed product.
D A and B
E None of the above.
D
12 The Statement of Work (SOW) is developed during the _____ cycle.
A Award
B Solicitations
C requirements
D contractual
E requisitions
C 来源:读书人-项目管理师考试