首页 诗词 字典 板报 句子 名言 友答 励志 学校 网站地图
当前位置: 首页 > 职业资格 > 项目管理 > 历年真题 >

PMP认证考试试题及答案(二十)

2010-09-08 
读书人职业资格频道职业资格考试专业网站 http://www.reader8.com/exam/zige/ 在10月24日要举行PMP第四次考试,离考试的时间越来越近,不知道考生有没有准备好,在这里编辑整理了一些PMP的练习题,希望能对考生有所帮助。也

读书人职业资格频道 职业资格考试专业网站 http://www.reader8.com/exam/zige/

在10月24日要举行PMP第四次考试,离考试的时间越来越近,不知道考生有没有准备好,在这里编辑整理了一些PMP的练习题,希望能对考生有所帮助。也希望考生能顺利通过考试。 1. on november 1, $1000 worth of work on task a was supposed to have been done (bcws); however, the bcwp was $850. calculate the
schedule variance:
a. -100
b. 100
c. -150
d. 150
e. 0.85
ans: c
2. the quality risk _____ .
a. is minimized through continuous monitoring.
b. is considered a long term risk.
c. will be reflected in the in-service life of the project result.
d. b and c
e. all of the above.
ans: e来源:www.examda.com
3. the act of conducting or supervising the exchange of information is:
a. consulting
b. project management
c. communications management
d. communications enhancement
e. none of the above
ans: c
4. the core function of the project manager is
a. systems design
b. client interfacing
c. quality assurance
d. integration来源:考试大
e.
ans: d
5. the future value of an annual income flow of $1000 for 2 years at 10% is:
a. 2200
b. 2280
c. 2300
d. 2310
e. none of the above
ans: d
6. the initial cost of a product and the product's operation and maintenance costs _____ .
a. increases perceived value when balanced.
b. are incidental to each other because initial costs are "sunk"
c. decreases design costs as operation periods increase
d. provides perceived function value and product social dysfunction
e. are integrally related with each other because initial costs are "sunk".
ans: a
7. all of the following may hinder a person's ability to transmit/receive a message except:
a. unfamiliarity with topic
b. withholding information
c. assuming
d. noise读书人(www.Examda。com)
e. preoccupation
ans: a
8. quality improvement programs are normally associated with which two of the following?
a. juran and crosby
b. juran and deming
c. crosby and deming
d. deming and the japanese
e. crosby and the japanese
ans: d
9. the utility theory _____ .
a. considers risk propensity of the decision maker.
b. attempts to formalize management's risk considerations.
c. works well with decision tree analysis.
d. is considered highly theoretical.
e. all of the above.
ans: b
10. the document authorizing functional areas to charge against the project is the:
a. work authorization form
b. scope baseline
c. project charter
d. management plan来源:考试大
e. linear responsibility chart
ans: a
11. the purpose of a dummy activity in an activity-on-arrow diagram is to:
a. identify a task that could be replaced by another.
b. take the slack time into account.
c. show a task that is not necessarily needed.
d. denote a milestone.
e. show a dependency relationship.
ans: e
12. when planning, organizing, coordinating, and controlling a project an important human resources skill or ability would be
a. building multi-disciplinary teams
b. managing conflict
c. communicating orally and in writing with all levels of personnel
d. involving senior management
e. all are important
ans: e
来源:读书人-项目管理师考试
热点排行