  QUEST Assigning resources in an attempt to find the shortest project schedule consistent with fixed resource limits is called resource _____.

  A Allocation.

  B Partitioning

  C Leveling

  D Quantification.

  E None of above.

  A

  QUEST Smoothing out resource requirements from period to period is called resource _____.

  A Allocation.

  B Partitioning

  C Leveling.

  D Quantification

  E None of above.

  C

  QUEST Guidelines for estimating time durations include:

  A Assuming a normal level of labor and equipment.

  B Assuming a normal work week.

  C Using consistent time units

  D Using past actual durations as guides.

  E All or part of each of the above.

  E

  QUEST Which of the following networking methods allows us to show that the last 10% of one element cannot be completed until 62% of a previous element has been completed?

  A PERT

  B ADM

  C PDM

  D All of the above.

  E A and C only.

  C

  QUEST In the PDM, common constraints include:

  A Start-to-start

  B Finish-to-start

  C Finish-to-finish

  D B and C only

  E A, B, and C.

  E

  QUEST Activities with zero time duration are referred to as:

  A Critical path activites.

  B Noncritical path activities.

  C Slack time activities.

  D Dummies

  E None of above.

  D