  QUEST The most difficult decision for the executive sponsors to make at the end-of-phase review

  meeting is:

  A Budget allocations for the next phase.

  B Authorizing scope changes for the next phase.

  C Authorizing budget increases for the next phase based upon scope changes.

  D Canceling the project.

  E All of the above.

  D

  QUEST The financial closeout of a project dictates that:

  A All project funds have been spent.

  B No charge numbers have been overrun.

  C No follow-on work from this client is possible.

  D No further charges can be made against the project.

  E All of the above.

  D

  QUEST A project can best be defined as:

  A Series of non-related activities designed to accomplish single and multiple objectives.

  B Coordinated effort of related activities designed to accomplish a goal without a well-

  established end point.

  C Cradle-to-grave activities which must be accomplished in less than one year and consumes

  human and non-human resources.

  D Any undertaking with a definable time frame, well-defined objectives, and consumes both

  human and non-human resources with certain constraints.

  E All of the above.

  D

  QUEST The project scope/charter baseline includes:

  A Summary of background conditions defining the project.

  B Organization, authority and responsibility relationships.

  C Functions to be performed.

  D Resource requirement schedule including time estimates.

  E All of the above.

  E

  QUEST Scope reporting is the timely determination, _____, and _____ of project progress,

  status data, and transforming this into structured documentation (reports) necessary to judge

  project performance (reporting on work packages).

  A Recording, accumulation.

  B Recording, graphical display.

  C Accumulation, graphical display.

  D Graphical display, interpretation.

  E Interpretation, analysis.

  A

  QUEST The work breakdown structure (WBS) is an excellent tool for objective control and

  evaluation. Which of the following is generally NOT validated through the WBS?

  A Time, schedule and cost.

  B Management coordination and organization structuring.

  C Work methods and accountability.

  D Quality of work.

  E Risk and impact decision-making.

  D

  QUEST The scope baseline once established and approved, is used:

  A as the basis for making future decisions.

  B to accomplish verification measures.

  C to evaluate potential changes.

  D All of the above.

  E A and C only.

  D

  QUEST The identification, definition, and selection of the project objectives as well as the

  best approach to achieving the project objectives are indentified in the _____ phase of the

  project but first documented in the project _____.

  A Conceptual, charter/baseline.

  B Conceptual, master schedule.

  C Development, charter/baseline.

  D Development, master schedule.

  E Development, masterplan.

  A

  QUEST Project management/project planning is most closely aligned with:

  A Long range/strategic planning (5 years or more).

  B Intermediate range planning (1 to 5 years)

  C Short range/tactical planning (1 year or less).

  D All of the above.

  E B and C.

  E

  QUEST Management decision-making includes:

  A Analysis of alternatives.

  B Revisions/replanning.

  C Resource allocation.

  D Modification or updating of goals and objectives.

  E All of the above.

  E

  QUEST The "control points" in the work breakdown structure used for isolated assignments to work

  centers are referred to as:

  A Work packages.

  B Subtasks.

  C Tasks.

  D Code of accounts.

  E Integration points.

  C

  QUEST A task-oriented family tree of activities is a:

  A Detailed plan.

  B Linear responsibility chart.

  C Work breakdown structure.

  D Cost account coding system.

  E Work package description.

  C

  QUEST Management plans include all of the following except:

  A Organization of project.

  B Job descriptions.

  C Policies and procedures.

  D Linear responsibility charts.

  E Scope baseline.

  E

  QUEST A comprehensive definition of scope management would be:

  A Managing a project in terms of its objective through the concept, development,

  implementation, and termination phases of a project.

  B Approval of the scope baseline.

  C Approval of the detailed project charter.

  D Configuration control.

  E Approved detailed planning including budgets, resource allocation, linear responsibility

  charts and management sponsorship.

  A

  QUEST The process of choosing/documenting the best approach to achieve the project objectives is

  part of:

  A The scope baseline.

  B Scope authorization

  C Scope definition

  D Scope planning.

  E All of the above.

  D